Fermi said Monday it received the money due under a $200 million prepayment agreement for Project Matador, its planned Panhandle data center. The company disclosed the amount in its quarterly report. Its Nov. 23 SEC filing confirmed receipt and did not announce a signed tenant lease.
That lease matters. Fermi says Dec. 31 is the deadline to receive a notice to proceed from the Texas Tech University System before it can start building its data center facilities. One condition is a signed lease with a first-phase tenant for at least 200 megawatts. Texas Tech may terminate the 99-year ground lease if Fermi misses the deadline and gets no extension, according to Fermi’s quarterly report.
The prepayment agreement accompanied a nonbinding letter of intent with an unnamed prospective customer for about 600 megawatts.
Why Cody Campbell is being sued
In a Dallas County lawsuit reported by The Texas Tribune, former Fermi CEO Toby Neugebauer alleges that Texas Tech regents chair Cody Campbell used the ground lease to push him out after he turned down a business proposal from Campbell’s firm. Campbell denied the allegations in a statement to the Tribune.
Fermi told investors that Texas Tech demanded Neugebauer’s removal from his executive roles and warned of a possible default under the ground lease.
Taylor Goldenstein of The Texas Tribune reported that Neugebauer filed suit Nov. 9 in Dallas County district court and seeks more than $1 million. He alleges a conflict of interest and accuses Campbell of interfering with his employment contract, spreading false information and conspiring to remove him, the Tribune reported.
What Double Eagle proposed
In a text the Tribune reviewed, Campbell offered in October 2025 to join Fermi’s board or serve as executive chairman. In a November text, Neugebauer encouraged Campbell to get involved. Neugebauer told the Tribune he was trying to appease him.
A February draft reviewed by the Tribune proposed $150 million in stock options for Campbell’s oil and gas firm, Double Eagle. The draft also laid out potential rights tied to a gas pipeline, water infrastructure and real estate.
Campbell told the Tribune the allegations were “ridiculous and untrue” and declined to elaborate, citing the lawsuit. Fermi disputed the allegations and said Double Eagle submitted the proposal at Neugebauer’s invitation. Texas Tech declined to discuss the case. Chancellor Brandon Creighton told the Tribune he had confidence in Fermi’s new leadership and its ability to move the project forward.
What Fermi told investors
Neugebauer says he turned down the proposal in a March 23 call and that Texas Tech sent its default notice minutes later, the Tribune reported. In a June SEC filing, Fermi said the university system cited Neugebauer’s publicly reported conduct involving U.S. Commerce Secretary Howard Lutnick when it warned of a possible default and demanded his removal. The filing gives no timestamp for the notice and does not say who directed it.
Fermi removed Neugebauer as CEO effective April 17. The company terminated his employment for cause April 30, when he also lost his board seat. As Lubbock Lights reported in June, Neugebauer blamed Campbell for his ouster and publicly recommended Campbell’s Double Eagle partner, John Sellers, to lead Fermi.
Why the ground lease matters
The lease covers the Texas Tech land in Carson County where Fermi is developing Project Matador. The regents’ minutes show the board unanimously authorized final lease negotiations at its April 14, 2025, meeting in Lubbock. Campbell attended by video. The board elected him chair later in that meeting. The 99-year lease was signed May 14.